Gov’t Builds Jagoi Babang Border Post in Kalimantan

By Office of Assistant to Deputy Cabinet Secretary for State Documents & Translation     Date 22 September 2021
Category: News
Read: 563 Views

Source: PR of Ministry of Public Works and Public Housing

Ministry of Public Works and Public Housing is completing the construction of the Jagoi Babang Border Post (PLBN) in Bengkayang regency, West Kalimantan province.

Minister of Public Works and Public Housing Basuki Hadimuljono said that the development of the border area is in line with the directives of President Joko “Jokowi” Widodo in supporting the socio-economic activities of communities at Indonesian borders.

“The PLBN is not only an entry gate but also part of regional economic growth center that can improve the welfare of communities living in border areas,” Basuki said as quoted by the Ministry’s website, Wednesday (09/22).

The construction began on November 27, 2020 with a budget of Rp207.35 billion, financed by the 2020-2022 multi-year State Budget. The construction progress has reached 26.71 percent and it is expected to be completed on July 19, 2022.

The data recorded by the Aruk Immigration Checkpoint (TPI) in March 2020 shows that there are 100-150 people passing through Jagoi Babang PLBN per week.

The Jagoi Babang PLBN has a strategic value as the gate of Indonesia because it is only 60 kilometers away from the State Capital of Sarawak, East Malaysia which can be reached in 1.5 hours. Meanwhile, the distance from Pontianak to the PLBN is 270 kilometers or about seven hours by car.

Previously, the Government had completed the construction of three PLBNs in West Kalimantan, namely Entikong PLBN in Sanggau regency, Aruk PLBN in Sambas regency, and Badau PLBN in Kapuas Hulu regency. (Public Relations of Ministry of Public Works and Public Housing/UN)